150K Manufacturing Facility
150K Manufacturing Facility
Renovation and new 150,000 square foot addition to manufacturing facility and offices.
- Design build project
- New 69kv/12MW prime meter substation.
- 15KV switch lineup.
- Add four 4000A pad mount transformers/MDPs
- Relocate tank farm including hydrogen tank.
- Relocate existing and wire new production lines using 1000’+ new busduct.
- Provided value engineering throughout the project.
- Maintain power for continuous production throughout project.
Project Details: Medina, Ohio
150,000 Square Feet